Sewer and Drainage Projects

West Porpoise Bay Area A02 Sewer Expansion: April - November 2018

The District of Sechelt has received funding from the Clean Water and Wastewater Fund for the expansion of its sanitary sewer system into Sewer Infill Area A02. Watch for road closures and detours during construction. Please obey flaggers. This project has been split into three phases.

Phase I:

Area A02 - Phase I has been awarded to BA Blacktop. Construction is underway and scheduled to be complete by the end of the year. 

November 9, 2018 Update:

  • Blasting has completed and sanitary main installation to be wrapped up by the end of the day.
  • Pressure testing the sewer main and paving to be completed by November 16.

November 1, 2018 Update:

  • Camera videoing of the new main on November 5 and 6
  • Blasting tentatively scheduled for November 6 on Lookout Ave

October 17, 2018 Update:

  • Waiting for firm date from blasting company to complete Lookout Ave Sani Main, expect last week of October or early November.
  • Internal video of sewer main will need to be done after Sani Main is complete. 

Phase II & III:

Area A02 - Phase II has been awarded to Bear Creek Contracting Ltd. Construction is scheduled to start December 2018 and is expected to be complete by Spring 2019. 

Please contact the District of Sechelt Engineering department for more information. Some lots may not be serviced as part of this project, and will be serviced under a future grant. 604-885-1986


1636574296810891759 

West Sechelt Area A06 Sewer Expansion

Area A06 has been awarded to Bear Creek Contracting Ltd. Construction is underway and is scheduled to be complete by mid-January 2019.

November 9, 2018 Update:

  • Blasting along Wakefield Road is underway between Acorn Road and Norwest Bay Road and is expected to continue through until next week. Residents directly affected by the blasting are recommended to listen carefully for the warning horn prior to ignition and stay clear of the construction site while blasting occurs. 
  • Sanitary sewer main and sanitary service tie-ins are to continue along Wakefield Road from Acorn Road to Norwest Bay Road
  • Ditching repairs and erosion control measures to be completed along Wakefield Road north of Highway 101.

November 1, 2018 Update: 

  • Blasting is tentatively scheduled for November 5 on Wakefield Road near the Acorn Road intersection. 
  • Installation of new sanitary sewer pipe will continue on Wakefield Road heading toward Norwest Bay from Acorn Road.

October 19, 2018 Update: 

  • Gowland Road work the week of Oct 22 includes: complete installing service tie-ins from sanitary main to property line (estimated completion Oct24), site clean up, 
  • Wakefield Road: waiting for blasting permits from Fortis. Blasting to begin when permit received. Residents in immediate area of blasting will receive written notice 24 hours prior to blasting. Site clean up and shoulder work to continue.

October 23 Update:

  • Work begins today on Wakefield Road starting at 5619 and working toward Norwest Bay Road
  • Service installs will be complete on Gowland Road by evening of Oct 24
  • clean-up on Wakefield Road and Gowland Road will be complete by the end of the week
  • Bear Creek crew is working on 3 week on and 1 week off schedule so no work will take place the week of Oct 29
  • Blasting MAY begin November 6

October 17 Update: 

  • Crews are currently installing sanitary sewermain on Gowland Road by 6523 heading north. Expect to be completed sewer main install by/on Oct 20th with service tie-ins left to install next week.
  • Further work on Wakefield Road, Anchor Place, Pickleball Court and Acorn Road cannot proceed any further without a blasting permit from Fortis Gas. Hoping to receive permit early next week. 

Please contact the District of Sechelt Engineering department for more information - 604-885-1986.